Capacity booking: The market is picking up noticeably
Since 19 March 2026, producers, large-scale consumers, suppliers and traders have been able to make binding bookings for entry and exit capacities on the core hydrogen network up to seven years in advance. This is based on a market information package published by the network operators on 5 March 2026, which sets out the cluster structure and booking process.
By the deadline of 23 July 2026, market participants in the network clusters had reserved just under 6 GW of capacity subject to payment. This represents a doubling compared with the baseline figure and exceeded the network operators’ expectations. According to FNB Gas, the core network is now in the initial phase of commercial marketing.
A critical assessment
As dynamic as capacity booking is proving to be, the warning signs along the rest of the value chain are all the more evident. In a special report published at the end of October 2025, the Federal Audit Office stated that the German hydrogen strategy did not meet key economic viability criteria, despite the fact that around 4.3 billion euros in funding was made available in 2024 alone, and more than 3 billion euros in 2025. It called for a reality check and a Plan B, as sticking to the current course jeopardises climate targets, industrial competitiveness and federal finances in equal measure.
Wolf-Peter Schill of the German Institute for Economic Research (DIW) describes the situation as sluggish across all sectors. Regulatory uncertainty, high investment and operating costs, and a low willingness among customers to pay are repeatedly cited as key obstacles.
The legislature has responded to one of these obstacles: the Hydrogen Acceleration Act, which came into force in April 2026, classifies the production, storage, import and transport of hydrogen as being in the overriding public interest until 2045, shortens approval times and introduces fully electronic procedures. However, this does nothing to address the economic obstacles.
Outlook: The Network Development Plan as the next strategic step
Faster procedures thus answer the question of ‘how’, not ‘how much’. The latter is decided elsewhere. The Gas and Hydrogen Network Development Plan 2025, which was put out for consultation in March 2026, builds on the Hydrogen Core Network approved in 2024 and sets out additional measures up to 2037. Based on the current scenario framework, which is heavily oriented towards reported industrial demand, the plan envisages 7,007 kilometres of new hydrogen pipelines with an investment volume of around 20.1 billion euros – partly as a supplement to, and partly as a continuation of, the core network already approved.
Despite unresolved issues regarding production, storage and off-take, the core network remains the key lever of the National Hydrogen Strategy: as capacity reservations increase, a robust database is emerging for the first time showing where actual demand is arising and where policy needs to be adjusted.